Another week of intensive work is behind us! What happened on the KST IV construction site between 1–5 June?
This week, our teams were working simultaneously on many fronts of the project.
On Strzelców Street, we rerouted the stormwater drainage system and adjusted the manholes in preparation for future asphalting. On Jancarza Street, we introduced a temporary traffic organization and began dismantling the road surface, opening the way for the next stages of work.
Roadworks are progressing intensively in the southern part of the project. On Młyńska Street, we completed work on the stormwater system, are building the aggregate and bituminous base layers, and are carrying out paving works. Paving works are also underway on Łąkowa and Ugorek Streets. Road construction continues as well on the access road to the office buildings on Lublańska Street.
Inside the tunnel, installation of granite flooring, ceiling cladding, and jet fans is ongoing.
Our electrical teams continue installing traffic lights and street lighting at additional locations along the route.
Thank you for your patience, and stay tuned to our profile for the latest updates from the construction site!