The third month of construction of the tramway to Mistrzejowice is behind us. We started work on the construction of the underground stop “Polsad Roundabout” and prepared the area for the new traffic organization. What else did we accomplish in September?

The third month of construction of the tramway to Mistrzejowice is behind us. We started work on the construction of the underground stop “Polsad Roundabout” and prepared the area for the new traffic organization. What else did we accomplish in September?

Earlier this month, on September 7, the first Construction Council was held with the participation of the public and journalists, at which the construction management summarized the progress to date and announced upcoming work.

In mid-September, preparations for the construction of the underground stop “Polsad Roundabout” began. First of all, we focused on performing the necessary control digging and preparing the working platforms for the deepening machine.

We also continued the reconstruction of sewer, water, telecommunications and energy networks.

Until the end of September, we conducted visual inspections of buildings and apartments located in the project’s zone of influence. We inventoried nearly 500 apartments.  

What are we doing in October?

At the beginning of October, we began sinking more than 20-meter-deep trenches near the Polsad Roundabout and creating the first diaphragm walls of the underground station.

Starting October 21, a new traffic organization will be in force. There will be closures and narrowing of road lanes on Lublanska Street, Młyńska Street, and Bora Komorowskiego Avenue, as well as changes in the relationship with priority of travel or sectional exclusions of pedestrian and bicycle routes. More information can be found [here].

Work is still on hold in the vicinity of Lublańska Street (west side) and Meissnera Street (near Pszona Street). Vegetation cutting in these areas will be possible after obtaining formal approvals of changes made to the detailed design from the Public Entity.

Enjoy a short video documenting the third month of work: