The completion of works on Dobrego Pasterza is getting closer!
Only a few days remain until the street is reopened — we’re planning it for December 5 at 22:00. What have we done over the past week?
- Bituminous layers have been laid on 300 meters of the roadway, and by Thursday we will finish the remaining 450 meters.
- Tomorrow, December 2, we will complete the construction of the curbs.
- We are finalising work on the tram tracks — the tram crossing near Biedronka is already finished, and the one at Krzesławicka Street will be completed by the end of the week.
- By the end of the week, we will also prepare the traffic organisation — vertical signs and road markings. We are also finishing work on the bus bays. Due to the required 28-day curing period after concreting, buses will still have to stop on the roadway for a few more weeks (except for the bay near the Municipal Guard building, which was completed earlier).
We’re really close now – thank you for sticking with us!