Partial closure of Miechowity Street

In connection with the construction of a new route of the Dominican Sudo as part of the Tram to Mistrzejowice project, traffic organization in the area of Mlynska and Miechowity streets will change starting March 16. Miechowity Street will be closed, and there will be narrowing on Mlynska Street. 

What will change?   

  • The existing switch on Mlynska Street will be moved north, towards the Polsad traffic circle.  
  • At the connection of Miechowity Street with Mlynska Street, vehicular traffic will be closed – a detour will be possible through Stanislaw ze Skalbmierza Street. At the same time, public transportation will run in this place on the current route and shuttle traffic will be introduced on a paved widening, available only for public transport vehicles and construction.
  • The bus stop “Miechowity 03” will be moved to the intersection of Bohaterów Wietnamu Street and Młyńska Street.

The new traffic organization will be introduced on March 16, starting at 5:00 am, and will last until August.

Update on 15.03.2024:

We inform you that in connection with Thursday’s field meeting (14.03.2024) of representatives of the Board of Roads of the City of Krakow, the Municipal Traffic Engineer, the Board of Public Transportation, the contractor and the public party, a decision has been made to maintain the possibility of entering passenger cars from Mlynska Street into Miechowity Street. The MIR has pledged to analyze and approve the proposed changes as soon as possible. In turn, the contractor is ready to implement the corrections approved by the traffic organizer.

At the same time, we emphasize that due to the complexity and extensiveness of the work related to the reconstruction of the Dominican River, the exact location of which will be known at the time of the uncovering after the COR, it may be necessary to return to the original design of the temporary traffic organization, i.e. to make the entrance to Miechowity Street available only to public transport vehicles and the construction of the

Czytaj dalej

Summary of work in February

This is the eighth month of work on the construction of the tram line to Mistrzejowice. What is the progress so far and what awaits us in March? We bring you the answers.

Due to the ongoing construction of the tunnel, a temporary traffic organization (COR stage 2.3) was introduced on February 24. There were closures and narrowing of roadways. On Lublańska Street, traffic between the Polsad traffic circle and the Barei traffic circle will only travel on the western roadway, where one lane for each direction has been designated. In addition, there is a temporary intersection with Lublańska Street at the level of the exit from Promienistych Street, where vehicle traffic from and to Bora-Komorowskiego Avenue is redirected. More.

Intensive work on the rebuilding of the Dominican Sudol continued throughout the month. By the end of the month we had installed 87 prefabricated elements, which give a total length of as much as 174m of new channel. More.

Three sessions of the Construction Council were held this month (January 1, 15 and 29), attended by representatives of the Private Partner and Local Government Entities, including the Councils of Districts III Prądnik Czerwony and XV Mistrzejowice, and interested residents.   

At the end of February, a meeting was held with residents regarding plantings in the Lublańska Street area. Together with representatives of the Board of Urban Greenery in Krakow, we discussed the details in terms of species of trees and shrubs, their exposure and optimization of the layout that meets the needs of residents.

What will happen in March?

In the middle of the month, it is planned to implement temporary traffic organization stage 2.4. The changes will apply to Mlynska Street and move the current switch to the north. In addition, the intersection of Miechowity Street and Mlynska Street will be excluded, and access will be via a detour through Stanislaw ze Skalbmierza Street.

We are beginning preparations and leveling of the ground for the performance of reinforced concrete work on the “Polsad Roundabout” station, and we will weld the heads of the carboys, i.e. the target pillars supporting the station floor. In March, we will also begin the sinking of diaphragm walls at the “Rondo Młyńskie” station and the KST turnout chamber. This will be the start of construction work at this stage of tunneling works. In addition, the work will also include the construction of platforms at the Mlynski traffic circle, under the flyover along Bora Komorowskiego Street and the excavation for their construction on Lublanska Street.

We will continue work related to the Dominican River Sudo, which includes, among other things, the further installation of prefabricated elements and the gutting of the western section of Mlynska Street. 

As in previous months, the reconstruction of numerous underground networks will continue.

Below is a video documenting the eighth month of work:

Czytaj dalej

Obstructions to pedestrian traffic on Meissner Street

As of Monday, March 4, pedestrians on a section of Meissner Street will face difficulties. Traffic will be redirected from the sidewalk located on the west side to the east sidewalk. The difficulties will last a week. 

Due to preparatory work related to the reconstruction of underground networks, as of Monday, March 4, the sidewalk on Meissnera Street between the pedestrian crossing by the Wieczysta Krakow Sports Club stadium and the pedestrian crossing on Chałupnika Street will be closed. 

The obstructions will last for a week, until Monday, March 11.

Czytaj dalej

The world’s longest tram line

The tram is undoubtedly one of the most comfortable and popular means of transport. Where on the map can we find the place where we can savour such a journey for the longest time? It turns out that we don’t have to look far.

Kusttram-the world’s longest tram line-is located in Belgium. It is an intercity tram system that connects Adinkerke to Knokke-Heist railway station, running through Nieuwpoort, Ostend and Zeebrugge. The record-breaking line is 67 km long and consists of 67 stops. The journey time on the low-floor tram is 2 hours 30 minutes.

An added bonus of this route is the picturesque views. The Custtram runs along the Belgian coastline and tram passengers can see the North Sea from the windows of the carriages right next to the track. Due to its location, the line is commonly referred to as the ‘beach tram’ or ‘coastal tram’. During the peak summer season, the depots carry up to 3 million passengers a day.

The line is hugely popular and an extension is envisaged as part of the Neptune plan. The extension would reach Dunkirk in France and Breskens in the Netherlands. The narrow-gauge route has been in existence for 139 years. It has been continuously modernised, with the most recent section opened in 1998.

What is the longest tramway line in Poland?

Today, the longest tram line can be found in Warsaw. It is a tram with the number 10, which runs for 24.5 km, stops at 54 stops and has a journey time of 82 minutes.

Czytaj dalej

History of trams in Kraków

Trams not only serve as a convenient and environmentally friendly means of public transport. For the people of Krakow, they are an important part of the city’s culture and history. Almost 123 years have passed since the first run of Krakow’s electric tram, but the origins of public transport go back a little further.

How did it all begin?

The year 1875 is considered the beginning of public transport in Krakow, when the first regular horse-drawn omnibus line was launched. Its route started from under the Main Railway Station and ended at Podgórski Bridge in the Kazimierz district.

The history of the trams themselves begins in November 1881, when the City Council of Krakow, under an agreement concluded with the Belgian Bank, granted permission for the “installation and maintenance of an iron railway called the tramway”. A year later, the first ceremonial run of the narrow-gauge horse-drawn tramway took place, and proceeds from ticket sales were donated to the construction of the Adam Mickiewicz monument.

The first tram crew ran along the route from the railway station to Mostowa Street in Kazimierz, where a tram depot was built. The carriages came in winter and summer versions and were divided into two classes: I and II. By1900, the horse-drawn tramway carried over 1.5 million passengers in Krakow.

Electrification

Electric trams appeared somewhat later. The commissioning of the first narrow-gauge tram line with a fleet of 17 electric carriages from the Wagon and Machine Factory in Sanok took place in 1901, and the ceremonial opening was performed by the city mayor Józef Friedlein. The success of electrification meant that from 1902 trams in Krakow were already running on 4 lines.

The following years also brought many important changes. As a result of the First World War, a large number of men were mobilised for the front and around 180,000 people left the city. The perceived shortage of workers meant that women also became tram drivers from 1916 onwards. The reconstruction of the tramway infrastructure actively started after the end of the war. First, the tram cars and tracks were repaired. Subsequently, the tram traffic system was changed from left-hand to right-hand traffic, and by 1925 there were already six tram lines in operation.

Czytaj dalej

Changes in traffic organization on Lublańska Street

Drivers in the northern part of Krakow are facing further temporary changes to traffic organisation. In connection with the ongoing construction of the tram line tunnel to Mistrzejowice, from 24 February closures and narrowing of the carriageway will appear on Lublańska street.

What will change? 

  • On Lublańska street traffic between the Polsad roundabout and the Bareja roundabout will use the western carriageway, which will have one traffic lane for each direction.
  • The eastern carriageway of Lublańska street from the Polsad roundabout to the Barei roundabout will be completely closed to traffic. 
  • Vehicular traffic from and to Bora-Komorowskiego Avenue will be redirected to the temporary intersection with Lublańska Street at the level of the exit from Promienistych Street,
  • The bus stop Olsza II 02 at Lublańska Street will be moved approx. 30 m to the north.

Temporary traffic organisation south of Miechowity Street will remain unchanged (stage 2.2): [link].

Temporary traffic organisation stage 2.2

The new traffic organisation will be introduced on 24 February, starting at 5.00am.  

Czytaj dalej

Replanting of trees as part of the construction of KST IV

With the completion of tree replanting for the construction of the tram line to Mistrzejowice, it is worth taking a closer look at the process. Here is a brief overview of how the trees were replanted. 

When to report trees?

The best time to replant trees is when they are dormant, i.e. early spring or late autumn and winter, when the temperature outside is positive and the soil is not frozen. During these seasons, trees are dormant, their growth and metabolic activity are limited.

What kind of trees are replanted? 

Due to their greater adaptability, mainly young trees are transplanted. They usually have smaller roots and are less complicated to transport, making the process less stressful for them.

Old trees, due to their extensive root system and longer life span, may prove less resistant to transplanting and are less likely to adapt to their new environment.

According to estimates, the limiting age that gives a prognosis for the adaptation of a transplanted tree is 20-25 years. For older trees, their chances of survival fall below 30 percent.

Replanting trees step by step

  • Assess the health of the tree, its age, size and root characteristics.
  • Reducing the crown – this will allow the plant to focus on re-rooting rather than feeding the shoots and leaves with nutrients.
  • Delineating and digging a trench at the selected target location.
  • Using a transplanting machine to precisely dig up the tree with an eye to minimizing root damage. After digging out the tree with the soil stock, the root ball is secured with a jute bag.
  • Transporting the tree and placing it in the hole dug earlier.
  • Stabilizing the trunk with stakes – this will prevent the tree from falling over.
  • Regular monitoring of the tree’s condition.

As a Private Partner, we replanted 42 trees (their location is marked in red on the map). The remaining 47 trees were replanted by the Urban Greenery Board (3 trees are in the process of replanting). 

Czytaj dalej

BIM technology

The construction of a tunnel as part of the emerging tram line to Mistrzejowice is one of the biggest engineering challenges of the project.  One of the key aspects is the use of BIM technology. What does it involve? We explain.

Building Information Modelling (BIM) is an advanced method of creating, managing and analysing building project information that contains highly detailed data and covers a wide range of processes. BIM brings together all relevant project information resources (technical, geometric, cost, other) to provide a comprehensive platform.

What it means, or say it “not in engineering terms

BIM is a technology used in the construction industry to help create, manage and analyse information about buildings or infrastructure in a digital and 3D way. Imagine a building is like a jigsaw puzzle, but instead of using cardboard pieces, we use virtual elements that can be moved, rotated and adjusted in any way.

In BIM, each element of a building is modelled in 3D. At the same time, each of these objects has data associated with it, such as materials, dimensions, technical properties or cost information. It is as if we added to each element with a description of what it relates to what it can be used for.

This technology enables collaboration between the various professionals involved in the construction process, such as architects, engineers, plant designers or builders. With BIM, they can work on one common model, which facilitates communication and eliminates errors due to inconsistencies between different documents or drawings.

In addition, BIM allows different scenarios to be simulated and the impact of changes on the entire project to be analysed, helping to make better decisions at each stage of construction. In other words, with BIM we can plan, design and build better, leading to more efficient construction projects.

In PPP projects, the partner is responsible for comprehensive implementation from design to construction to maintenance for a specified number of years. In this case, there is a need for effective communication and data flow between many stakeholders such as the client, designers, administration, operators, managers of individual infrastructure elements, contractors, internal departments of the company, supervision inspectors, subcontractors. 

With access to extensive data, teams from different trades can work on a project simultaneously, seeing changes in real time. BIM technology improves the efficiency of the construction process by reducing the risk of errors and clashes, optimising costs and speeding up project delivery. In the context of the construction of the Tram to Mistrzejowice, the implementation of BIM has become essential to achieve a high level of safety and to run the project to the highest quality standards.

Czytaj dalej

Construction of Tram to Mistrzejowice kicks off

The first preparatory work for the redevelopment of the technical infrastructure and the construction of the tram route will begin this coming Monday: 3 July.

In the coming weeks, our activities will primarily involve site preparation and the implementation of earthworks related to the redevelopment of underground infrastructure. These works will also involve cutting down trees in areas that interfere with the planned new routes of this infrastructure. Nevertheless, our primary goal is to avoid trees and shrubs that are located in areas where we are analyzing the possibility of making changes. This is aligned with the expectations of residents.

The mayor of Krakow declared on Thursday, 29 June, that within a month final decisions will be made on the possibility of taking into account the demands of residents. Until the answers are published, we will continue our work: avoiding areas that may be subject to adjustments.

At first, we will focus on work on the southeast side of the Polsadu Roundabout, heading towards the Młyńskie Roundabout. Then we will work in the area of Lublańska Street on the eastern side towards the Barei Roundabout, and later from the Barei Roundabout to Mistrzejowice. Finally, work will be carried out from the Młyńskie Roundabout to Jana Pawła II Avenue and in the area of Lublańska Street on the west side due to the consideration of residents’ demands.

Starting Monday, signs will be located along the route of the project: informing of construction works and tree cutting. In connection with the first stage of the temporary traffic organization, there will be local narrowing of road lanes and temporary exclusions of pedestrian and bicycle routes.

Every effort will be made to minimize inconvenience and ensure the safety of residents during the implementation of these works.

Czytaj dalej
Wizualizacja tramwaju

Tramway to Mistrzejowice with environmental agreements

New plantings, green tracks and stops, revitalization of the terminus: we know what the green development around the tram route to Mistrzejowice will look like. Residents will gain a modern and sustainable means of transportation, providing an alternative to cars.

The tram route to Mistrzejowice project has received a positive opinion from the Regional Directorate for Environmental Protection (RDOŚ). This is the last step before obtaining a construction permit, allowing work to begin. – The decision just issued by the RDOŚ as part of a reassessment of the investment’s impact on the environment confirms that it complies with the environmental decision issued and can be implemented without hindrance. Among the issues assessed were those concerning greenery, which is of great importance to the local community,” specifies Krzysztof Dziobek, contract director at Gülermak.

The contractor’s individual approach to each specimen and the personal involvement of the construction management made it possible to preserve nearly 200 trees intended for removal in the original design (including dozens growing along Meissnera Street). Positive changes were initiated by a change order issued by a public entity last May, aimed, among other things, at reducing noise pollution and thus the number of noise barriers. In the end, the tree stand management project submitted to the RDEP indicated that there were 1,059 trees in conflict with the planned infrastructure. Investigations of the phytosanitary condition showed that about 60% of them have defects, such as mechanical damage to the bark, drought, decay, frost foliage, traces of pest feeding or significant deviation from the vertical. Seventy-one young, healthy specimens were selected for replanting. 26 of them are already growing in new locations, while the remaining 45 will be moved to their target sites once construction begins. As much as 10,308 square meters of shrubs, flowerbeds and grasses will be added to the project site, more than 2,000 square meters more than the total area of all shrubs to be removed.

New tree plantings along the tram route to Mistrzejowice

– In accordance with the commitment, for each interfering tree we will plant a new one. Their location has been carefully planned to allow the plants to survive in demanding urban conditions, and in the future to provide shade for pedestrians, cyclists and public transport users. All the new plantings have been designed along the project, so there is no question of planting trees in unpopulated areas on the outskirts of the city, as contractors are often accused of,” adds Krzysztof Dziobek.

The selected tree species, including common oak and small-leaved linden, are resistant to pollution, drought, frost and salinity, so they will put down roots in the vicinity of the streetcar line for years to come. The trees designed for the stop platforms will be planted using an anti-compression system, which allows the roots to grow freely under the sidewalk. The private partner used a similar technology for the M2 line of the Warsaw subway.

Green revitalization of the terminus, track and stops

In addition, the project provides for green track using sedum mats along a 4.2-kilometer stretch of single track. These do not require watering or mowing, thus saving natural resources. The route will also feature 19 stops with green roofs, with a total area of 1,900 sqm, giving as much as 4,750 liters of water retention per year. Thanks to dense tree planting, the entire Mistrzejowice terminus will undergo a green transformation. Between the alleys there will be dozens of new trees, appropriately selected shrubs and grasses. The Młyńskie Roundabout will be decorated with a composition of maples, roses and ornamental grasses. A flower meadow will appear at the Barei Roundabout, and eight seedlings will be added to the acacia robinia. A rain garden will also be created adjacent to the traffic circle.

Current design sheets showing future land use along the streetcar line to Mistrzejowice are available at www.tramwajdomistrzejowic.pl

Czytaj dalej