Organization of bicycle and pedestrian traffic

In connection with the commencement of the next stage of construction as part of the Tram to Mistrzejowice project, from 17 July changes will be made to pedestrian and bicycle routes in the area of Meissnera, Młyńska and Dobrego Pasterza streets.

Along the eastern part of Meissnera Street, on the section from Sttaniec Street to the Młyńskiego roundabout, a separate pavement and a bicycle path will be transformed into a common pedestrian and bicycle route.

Between the Młyńskie roundabout and the Polsadu roundabout, the possibility of pedestrian traffic will be maintained, and bicycle traffic will be redirected by a detour in general traffic from Pilotów Street to Bora-Komorowskiego Avenue.

On the south-western side of the flyover, a bicycle crossing and a pedestrian crossing will be restored (access only to the construction site). The crossing will allow cyclists to join the existing bicycle path on the western side of the flyover.

Along the northern part of Dobrego Pasterza Street, on the section from the Barei roundabout to Aliny Street, a separate pavement and a bicycle path will be transformed into a common pedestrian and bicycle route.

The new traffic organization will be introduced on July 17, from 7.00 a.m.

Czytaj dalej

The next stage of the reconstruction of the heating network

We would like to inform you about the commencement of the next stage of the reconstruction of the heating network along the western part of Meissnera Street and the partial closure of the pavement.

The works will be carried out on the section from Ugorek Street to the crossing in the area of KS Wieczysta.

After the completion of technological works, the pavement will be made available for use on weekends.

The expected duration of the works is about 3-4 weeks.

Thank you for your patience and we apologize for any inconvenience caused.

Below is a map with the location:

Czytaj dalej

Reconstruction of the power grid in the area of 120-122 Dobrego pasterza Street

From next Tuesday, July 9, works related to the reconstruction of the power grid along the buildings at Dobrego Pasterza Street numbered 120-122 will begin.

Due to the location of the works, it will be necessary to occupy a part of the parking lot at the curb.

Please be careful and pay attention to the signage. Thank you for your understanding and we apologize for any inconvenience caused.

Czytaj dalej

Urgent reconstruction in the Łąkowa Street area

We would like to inform you that due to the change in the order of works, it is necessary to rebuild the heat pipe in the area of Łąkowa Street earlier.

The works will start next Monday, July 8, and will last 2-3 days. During this period, it will only be possible to enter Łąkowa Street from Meissnera Street, while the exit will be temporarily restricted.

We make every effort to minimize inconvenience, accelerating the progress of works.

Thank you in advance for your understanding and patience.

Czytaj dalej

The Sudół Dominikański flows with a new current

Work on Sudół Dominikański  has been completed – the underground river is already flowing with a new current. At the end of June, the waters of the stream were introduced into a chamber in the area of Miechowity Street, and then flowed through the entire length of the newly built canal, i.e. 388.65 m (including chambers approx. 400 meters). The reconstruction of Sudół Dominikański was one of the most difficult engineering tasks of the first stage of construction.

The project related to the construction of a tram line to Mistrzejowice assumed the liquidation of the existing fragment of the Sudół Dominikański stream on the section from the intersection of Młyńska Street and Macieja Miechowity Street to the connection with the canal running from the Młyńskie roundabout to the Prądnik River. At the end of June, Gülermak, the general contractor of the Tram to Mistrzejowice, reconnected the river current to a new riverbed. The reconstruction of this section of Sudole Dominikański cost about PLN 30 million.

The construction of a new underground channel is one of the biggest engineering challenges we have ever faced. Work in the city requires precise planning to disturb the daily life of residents as little as possible and at the same time ensure efficient organization on the construction site – says Lidia Śmierzchalska, construction works manager.

Sudół Dominikański will now run under some of the pavements and roadways. The river changed its location by about 8-10 meters to the west. It flows in a specially prepared riverbed, which consists of 189 prefabricated elements with a length of 2.0 m and an internal cross-section of 2.25 x 3.0 m. The weight of a single element is as much as 10.8 tons. Gülermak engineers chose the technology, using prefabricated elements that were joined directly on site. Thanks to this, it was possible to stage the works as part of the project and minimize the nuisance for residents.

Sudół Dominikański in the previous current ran exactly in the place where we are building the tunnel and the new road system.  This work front is now available to us. Thanks to this, by the end of August, we will build the western part of the roadway by the new Sudole Dominikański canal. Pedestrian and vehicular traffic will be redirected from the eastern part to free up space for the construction of the tunnel. As a result, we will be constructing diaphragm walls on the section Młyńskie roundabout – Polsadu roundabout – says Krzysztof Dziobek, contract director.

Intensification of works on the Mistrzejowice terminus

Meanwhile, intensive work is underway on the final section of the 4.5-kilometer tram line. In the area of the Mistrzejowice terminus, the voltage in the overhead contact line has been switched off. The wires were removed and the poles were dismantled.  From Monday, June 24, the loop has been out of use. Work is underway on the dismantling of the track, which involves, among others: cutting rails, dismantling sleepers, unfastening rails from sleepers. Work is underway to remove the entire track infrastructure from the Mistrzejowice loop in order to start troughing the track for the new track. All works are carried out under constant sapper supervision, which will last until the end of works in this area.

Czytaj dalej

Night-time aggregate operation in the area of the car park at KS Wieczysta

We ask for your understanding of any inconveniences related to the night operation of the generator in the area of the KS Wieczysta car park. We would like to inform you that during the heating of heating pipes, an uninterrupted process of work is necessary. The technology requires the aforementioned continuity of work to ensure the highest quality of workmanship and safety of operation.

We make every effort to ensure that the works run smoothly and according to schedule. Night operation of the unit is planned until Wednesday inclusive.

Thank you for your understanding and patience. We are convinced that the final effect in the form of a new tram line to Mistrzejowice will bring many benefits to our community.

Czytaj dalej

Reconstruction of the Mistrzejowice tram terminus

We would like to remind you that from next Monday, June 24, the Mistrzejowice tram terminus will be closed.

Changes will be introduced in the operation of the KMK line:

  • line 9 will run along the temporarily changed route: Nowy Bieżanów P+R – … – Rondo Grzegórzeckie – Pokoju Avenue – Czyżyńskie Roundabout – … – Piastowskie Roundabout – Os. Piastów;
  • line 14 will run along the temporarily changed route: Bronowice – … – Mogilskie Roundabout – Mogilska Street – Jana Pawła II Avenue – Czyżyńskie Roundabout – … – Hippokratesa Roundabout;
  • line 16 will run along the temporarily changed route: Bardosa – … – Rondo Piastowskie – Os. Piastów.

After the completion of the shutdown of the tram track along Powstania Warszawskiego Avenue, it is assumed that line 14 will be directed to the Os. Piastów, and line 9 to the Rondo Hipokrates tram terminus.

Details related to the functioning of public transport are updated on the website of the Public Transport Authority in Krakow.

Czytaj dalej

Reconstruction of the heat pipeline at Ugorek Street

We would like to inform you that from next Tuesday, June 18 to Friday, June 21, there will be difficulties in the area of the intersection of Meissnera and Ugorek streets.

Due to the ongoing works on the reconstruction of the heat pipeline network and the need to go through the heat pipeline under the road, on Tuesday – Wednesday it will only be possible to enter Ugorek Street from Meissnera Street. Exit from Ugorek Street into Meissnera Street is recommended by a detour. Then, from Thursday to Friday, only the exit from Ugorek Street will be possible. Entrance to Ugorek Street from Meissnera Street is recommended by a detour. Manual traffic management will be introduced.

We apologize for the inconvenience and thank you for your cooperation.

Below is the exact location.

Czytaj dalej

Reconstruction of the power grid at 118c Dobrego Pasterza Street

We would like to inform you that from next Monday, June 17, works related to the reconstruction of the power grid near the transformer station will begin. Due to the works, the access road to the internal car park with a barrier and access to the car park at block 118c at Dobrego Pasterza Street will be temporarily out of use.

Work on this section will begin on Monday between 7:00 and 8:00 a.m. and will last 14 days. Please do not block the entrance for the duration of the works. We apologize for the inconvenience and thank you for your cooperation.
Below is the exact location.

Czytaj dalej

Exclusion of 5 parking spaces at 118 Dobrego Pasterza Street

We would like to inform you that from next Monday, June 17, works related to the reconstruction of the power grid near the transformer station will begin.

Due to the works carried out at 118 Dobrego Pasterza Street, it is necessary to exclude five parking spaces from use.

Works on this section will start on Monday between 7:00 and 8:00 in the morning and will last 4 days.

Please do not park in designated places for the duration of the works.

We apologize for the inconvenience and thank you for your cooperation.

Below is the location of the excluded part of the car park.

Czytaj dalej