August on the Construction Site of the Tram to Mistrzejowice
The summer holidays were filled with intensive work, and August brought further changes visible to residents. The most important development was the restoration of tram traffic along Mogilska Street and al. Jana Pawła II. Thanks to this, tram service along this route resumed at the beginning of the school year, making it easier for passengers to reach schools and workplaces.
Roadworks Department
The roadworks team focused on constructing tracks and roadways at several locations simultaneously. Track construction was carried out at the intersections of Bohomolca, Marchołta, Kurzei, and Załuskich Streets, allowing for the continuation of additional segments of the new route. On Jancarza and Bohomolca Streets, paving works, sidewalk and bike path installation, and platform construction were continued.
On Meissnera, Pilotów, Młyńska, Dobrego Pasterza Streets, and near the Mistrzejowice terminal, work began on new bus platforms. These are essential elements to ensure comfortable transfers and accessibility for passengers, pedestrians, and cyclists in the future.
On Meissnera, Pilotów, Lubańska, Bohomolca, and Jancarza Streets, earthworks continued, and foundation layers for the new road and track structures were being laid. Bituminous layers were paved in sections along the above-mentioned streets and on parts of the Barei Roundabout carriageway.
Electrical Department
August was a very busy month for the electrical department. In addition to installing and equipping traction poles along the entire route, they carried out the construction of power supply cables and the reconstruction of the existing traction network in the area of al. Jana Pawła II and Mogilska. This prepares the infrastructure for the eventual installation of overhead contact wires and the final tram power supply.
At the same time, cable ducting for telecommunications operators and traffic signal systems was being built – this will ensure the proper operation of traffic management systems in the future. In many areas – including Meissnera, Pilotów, and Dobrego Pasterza Streets – conduits under roads and tracks, as well as protective cable pipes, were installed, securing the infrastructure for years to come.
Installation of new street lighting was also underway, with lamp fixtures appearing on Meissnera, Jancarza Streets and near the Mistrzejowice terminal.
Sanitary Department
The sanitary team was mainly responsible for relocating conflicting underground installations. On Meissnera Street, the gas pipeline, water supply, and sewer system were relocated at the intersection with Chałupnika Street – enabling continued paving and track works on this section.
Simultaneously, manhole adjustments were carried out across the construction site – these small details are essential to ensure the durability and safety of the final sidewalks and roadways.
Inside the tunnel, internal installation works were being carried out.
Bridge and Tunnel Department
This department continued reinforced concrete works on the tunnel structure – including under-slab excavation, wall and slab concreting, and insulation works. The fastest progress was made in sections where under-slab excavation enabled work to start on new construction fronts. Walls and corridors are now visible below the surface.
At Polsad Station, general construction and installation works were carried out on both levels, while at the Barei Roundabout and on Meissnera Street, the construction of entry ramp walls progressed.
Structural Department
The structural team worked on retaining walls and noise barriers. Reinforcement, concreting, and insulation allowed for the completion of several sections and the beginning of new ones. At the same time, excavations and piling were carried out for future barriers – although not as visually striking as the tracks, these elements are crucial in protecting residents from noise.
In some locations, noise barrier posts have already been installed, offering a glimpse of the route’s final appearance.
What’s Ahead in September?
In September, work will focus on the continued installation of sanitary and electrical infrastructure, as well as ongoing tunnel works. New street lighting will be switched on in sections already completed.
In the areas of Rondo Młyńskie and Rondo Barei, new traffic arrangements will be introduced to open up completed road sections. Intensive work will continue on sidewalks, bicycle paths, and platform construction. Asphalt paving will take place throughout the month.
Installation work in the tunnel will also continue – including water, sewage, and ventilation systems – which are necessary to begin finishing the station and equipping it with safety systems in the coming months.