Another month of construction on KST-4 is behind us!

Although January greeted us with exceptionally low temperatures, work has not slowed down!

For nearly two weeks, traffic on Meissnera Street has been running on the western carriageway, while demolition works have already begun on the eastern one. Although sub-zero temperatures have prevented us from carrying out road works, our engineers remain busy on other fronts. We are building stormwater and sanitary sewage systems, dismantling old surfaces, and carrying out earthworks and reinforced concrete works at the tunnel exits. In addition, a lot is also happening inside the tunnel, where, among other things, we are installing the track system.

We encourage you to watch the latest footage from the construction site and listen to Wojciech Janosz, our construction manager, who will give a detailed account of the activities carried out over the past month.